| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 0-E-U-13B | CIMBRA APARENTE EN MUROS DE CONTECION PARA RAMPAS ,ESCALERAS Y PASILLOS EN LOS ACCESOS PRINCIPAL Y DE SERVICIOS.INCLUYE MATERIALES Y MANO DE OBRA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16 MM | M2 | 0.350000 | $103.00 | $36.05 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 1.660000 | $1.37 | $2.27 |
| CLAVO | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.166500 | $16.60 | $2.76 |
| ACERO-01 | ALAMBRE RECOCIDO | KG | 0.500000 | $11.14 | $5.57 |
| SEPARADORES | Separadores | PZA | 3.000000 | $2.50 | $7.50 |
| DIESEL | DIESEL | LT | 0.600000 | $6.00 | $3.60 |
| MADERA D/PINO 3A | MADERA DE PINO DE 1A. | PT | 5.200000 | $7.12 | $37.02 |
| Suma de Material | $94.78 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Carpintero + 1Ayudante) | JOR | 0.220000 | $876.53 | $192.84 |
| Suma de Mano de Obra | $192.84 | ||||
| Costo Directo | $287.62 |