| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BKCV-EL-137 | CURVA CONDUIT PVC TIPO R-1 PESADO DE 75 MM X 90 GR | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CODOCPVCTP75 | CODO CONDUIT PVC TIPO PESADO DE 75MM | PZA | 1.000000 | $85.40 | $85.40 |
| PEGTANGITROS500 | PEGAMENTO TANGIT ROSADO , BOTE DE 500 ML | PZA | 0.035000 | $178.00 | $6.23 |
| LIMPIADOR-PVC-2 | LIMPIADOR PARA PVC , BOTE DE 250 ML | PZA | 0.030000 | $53.20 | $1.60 |
| ESTOPA | ESTOPA BLANCA | KG | 0.020000 | $16.30 | $0.33 |
| Suma de Material | $93.55 | ||||
| Mano de Obra | |||||
| CUADRILLA INST. 08.A | Cuadrilla de electricista ( Electricista + ayudante) | Jor | 0.028571 | $1,044.80 | $29.85 |
| Suma de Mano de Obra | $29.85 | ||||
| Auxiliar | |||||
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.024430 | $31.52 | $0.77 |
| Suma de Auxiliar | $0.77 | ||||
| Costo Directo | $124.17 |