| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EXT-32 | SUMINISTRO Y COLOCACION DE MURO DE .35 M. DE DUROCK 1.22 2.44, INCLUYE : , ACABADO CON PASTA BASECOAT ,POSTES METALICOS CAL. 26 , CANALETAS DE CARGA , MATERIALES , MANO DE OBRA , HERRAMIENTAS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| DUROCK TABLA CEMENT | DUROCK TABLA CEMENTO DE 1.22 X 2.44 M . | M2 | 2.100000 | $160.00 | $336.00 |
| DUROCK EXTERIOR | DUROCK EN FRANJAS DE 20 CM. DE ANCHO | ML | 2.550000 | $30.00 | $76.50 |
| POSTE 635 CAL.20 | GALVANIZADO | ML | 2.700000 | $10.15 | $27.41 |
| CANAL 635 CAL.20 | GALVANIZADO | ML | 0.900000 | $9.00 | $8.10 |
| BASECOAT | SACOS 22.5KGS. | KG | 6.355500 | $12.00 | $76.27 |
| ANCLAS HILTI. | ANCLAS HILTI | PZA | 3.000000 | $2.70 | $8.10 |
| FULMINANTES . | FULMINANTES | PZA | 3.000000 | $3.00 | $9.00 |
| ESQUINERO METALICO | ESQUINERO METALICO | ML | 0.500000 | $3.61 | $1.81 |
| TORNILLO 1/2 " TEK | PUNTA DE BROCA | PZA | 14.000000 | $0.15 | $2.10 |
| TORNILLO DUROCK | TORNILLO DUROCK | PZA | 18.000000 | $0.35 | $6.30 |
| PERFACINTA | PERFACINTA | ML | 2.100000 | $3.83 | $8.04 |
| Suma de Material | $559.62 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 31 | (1 Of. Yesero + 1 Ayudante) | JOR | 0.168550 | $859.54 | $144.88 |
| Suma de Mano de Obra | $144.88 | ||||
| Herramienta | |||||
| ANDAMIAJE | 0 | R/DIA | 0.150000 | $130.17 | $19.53 |
| FLETES Y MANEJO | FLETES Y MANEJO | (%)m | 0.100000 | $0.00 | $0.00 |
| Suma de Herramienta | $19.53 | ||||
| Costo Directo | $724.02 |