| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U-55-A | BASE DE DE BLOCK DE CONCRETO DE 3.63X2.54X0.40M RELLENANDO TODOS LOS HUECOS DEL BLOCK CONCONCRETO DE 250KG/CM2 CON MURO INTERMEDIO SEGUN CROQUIS PROPORCIONADO POR EL PROYECTO DEL SISTEMA DEL AIRE ACONDICIONADO INCLUYE TAPA DE CONCRETO DE LA MISMA RESISTENCIA ACABADO FINO Y DE 5 CM DE ESPESOR, CIMBRA MUERTA ,MATERIALES ,ELEVACION DE LOS MISMOS Y MANO DE OBRA.(EN AZOTEA DE RESTAURANT A 7.74M DE ALTURA). | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA D/PINO 3A | MADERA DE PINO DE 1A. | PT | 19.650000 | $7.12 | $139.91 |
| CLAVO | CLAVO DE 2 1/2" A 3 1/2" | KG | 1.380000 | $16.60 | $22.91 |
| DIESEL | DIESEL | LT | 4.610000 | $6.00 | $27.66 |
| ACERO-01 | ALAMBRE RECOCIDO | KG | 0.500000 | $11.14 | $5.57 |
| AGREGADO-003 | AGUA | M3 | 0.030000 | $40.00 | $1.20 |
| CONCRETO-03 | Concreto Premezclado resistencia normalF'c=250 Kg/Cm2 A.M. 3/4" SE INCLUYE revenimiento | m3 | 0.860000 | $896.80 | $771.25 |
| ACERO-03 | MALLA ELECTRO SOLDAD 6X6 6-6 . | M2 | 9.220000 | $13.44 | $123.92 |
| ANDAMIOS | ML CONSISTENTE EN DOS TIJERAS Y DOS CUARPOS /CADA METRO | ML | 8.000000 | $10.00 | $80.00 |
| GALLETAS O SILLETAS | GALLETAS O SILLETAS | PZA | 9.000000 | $1.50 | $13.50 |
| BLOCK SPLIT FACE | MEDIDA 20 X 20 X 40 | pza | 72.000000 | $8.86 | $637.92 |
| AGREGADO-003 | AGUA | M3 | 0.320000 | $40.00 | $12.80 |
| Suma de Material | $1,836.63 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Carpintero + 1Ayudante) | JOR | 1.500000 | $876.53 | $1,314.80 |
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones). | JOR | 0.750000 | $2,208.84 | $1,656.63 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 1.500000 | $876.53 | $1,314.80 |
| Suma de Mano de Obra | $4,286.22 | ||||
| Equipo | |||||
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOT. KHOLER 4 H. C/ OPERADOR . | HR | 1.000000 | $56.23 | $56.23 |
| Suma de Equipo | $56.23 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE. 1:5 | Mortero cemento arena 1:5 | M3 | 0.120000 | $717.66 | $86.12 |
| ANDAMIO METALIC3MTS | ANDAMIO DE 3 MTS DE ALTURA | DIA | 2.000000 | $51.42 | $102.84 |
| Suma de Auxiliar | $188.96 | ||||
| Costo Directo | $6,368.04 |