| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U-56-A | BASE DE DE BLOCK DE CONCRETO DE 2.45X1.60X0.40M RELLENANDO TODOS LOS HUECOS DEL BLOCK CONCONCRETO DE 250KG/CM2 CON MURO INTERMEDIO SEGUN CROQUIS PROPORCIONADO POR EL PROYECTO DEL SISTEMA DEL AIRE ACONDICIONADO INCLUYE TAPA DE CONCRETO DE LA MISMA RESISTENCIA ACABADO FINO Y DE 5 CM DE ESPESOR, CIMBRA MUERTA ,MATERIALES ,ELEVACION DE LOS MISMOS Y MANO DE OBRA.(EN AZOTEA DE RESTAURANT A 7.74M DE ALTURA). | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA D/PINO 3A | MADERA DE PINO DE 1A. | PT | 10.000000 | $7.12 | $71.20 |
| CLAVO | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.750000 | $16.60 | $12.45 |
| DIESEL | DIESEL | LT | 2.000000 | $6.00 | $12.00 |
| ACERO-01 | ALAMBRE RECOCIDO | KG | 0.150000 | $11.14 | $1.67 |
| AGREGADO-003 | AGUA | M3 | 0.100000 | $40.00 | $4.00 |
| CONCRETO-03 | Concreto Premezclado resistencia normalF'c=250 Kg/Cm2 A.M. 3/4" SE INCLUYE revenimiento | m3 | 0.460000 | $896.80 | $412.53 |
| ACERO-03 | MALLA ELECTRO SOLDAD 6X6 6-6 . | M2 | 3.920000 | $13.44 | $52.68 |
| ANDAMIOS | ML CONSISTENTE EN DOS TIJERAS Y DOS CUARPOS /CADA METRO | ML | 8.000000 | $10.00 | $80.00 |
| GALLETAS O SILLETAS | GALLETAS O SILLETAS | PZA | 4.000000 | $1.50 | $6.00 |
| BLOCK SPLIT FACE | MEDIDA 20 X 20 X 40 | pza | 48.000000 | $8.86 | $425.28 |
| AGREGADO-003 | AGUA | M3 | 0.320000 | $40.00 | $12.80 |
| Suma de Material | $1,090.61 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Carpintero + 1Ayudante) | JOR | 0.500000 | $876.53 | $438.27 |
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones). | JOR | 0.500000 | $2,208.84 | $1,104.42 |
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones). | JOR | 0.500000 | $2,208.84 | $1,104.42 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 1.000000 | $876.53 | $876.53 |
| Suma de Mano de Obra | $3,523.64 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE. 1:5 | Mortero cemento arena 1:5 | M3 | 0.072000 | $717.66 | $51.67 |
| ANDAMIO METALIC3MTS | ANDAMIO DE 3 MTS DE ALTURA | DIA | 2.000000 | $51.42 | $102.84 |
| Suma de Auxiliar | $154.51 | ||||
| Costo Directo | $4,768.76 |