| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U-17A | ESCALON DE CONCRETO DE F'c=200KG/CM2 DE 0.16X0.40X1.00M REFORZADOS CON MALLA 6X6:6/6 ACABADO LAVADO Y CON NARIZ CURVA DE 2" .INCLUYE MATERIALES Y MANO DE OBRA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-03 | MALLA ELECTRO SOLDAD 6X6 6-6 . | M2 | 0.510000 | $13.44 | $6.85 |
| AGREGADO-003 | AGUA | M3 | 0.067000 | $40.00 | $2.68 |
| Suma de Material | $9.53 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.250000 | $876.53 | $219.13 |
| Suma de Mano de Obra | $219.13 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.040000 | $981.74 | $39.27 |
| Suma de Auxiliar | $39.27 | ||||
| Costo Directo | $267.94 |