| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U-40A | DESCANSO DE CONCRETO DE F'c=250 KG/CM2 DE 0.17M DE PERALTE Y DE 1.22X1.22M CON NARIZ SEMICIRCULAR Y FORRADOS DE CERAMICA INTERCERAMIC ASENTADA CON ADHESIVO INTERCERAMIC.INCLUYE CIMBRA, MOLDURA MATERIALES Y MANO DE OBRA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16 MM | M2 | 0.350000 | $103.00 | $36.05 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 1.660000 | $1.37 | $2.27 |
| CLAVO | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.166500 | $16.60 | $2.76 |
| ACERO-01 | ALAMBRE RECOCIDO | KG | 0.500000 | $11.14 | $5.57 |
| SEPARADORES | Separadores | PZA | 3.000000 | $2.50 | $7.50 |
| DIESEL | DIESEL | LT | 0.600000 | $6.00 | $3.60 |
| MADERA D/PINO 3A | MADERA DE PINO DE 1A. | PT | 5.200000 | $7.12 | $37.02 |
| ACERO-02 | ACERO REF.VAR.DIAM. | KG | 10.500000 | $8.00 | $84.00 |
| ACERO-01 | ALAMBRE RECOCIDO | KG | 0.280000 | $11.14 | $3.12 |
| AGREGADO-003 | AGUA | M3 | 0.300000 | $40.00 | $12.00 |
| CONCRETO-003 | SERVICIO DE BOMBEO | M3 | 0.105000 | $150.00 | $15.75 |
| CONCRETO-03 | Concreto Premezclado resistencia normalF'c=250 Kg/Cm2 A.M. 3/4" SE INCLUYE revenimiento | m3 | 0.105000 | $896.80 | $94.16 |
| Suma de Material | $303.82 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Carpintero + 1Ayudante) | JOR | 0.100000 | $876.53 | $87.65 |
| CUADRILLA NO. 18 | ( 1 Of. Fierrero + 1Ayudante). | JOR | 0.050000 | $876.53 | $43.83 |
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones). | JOR | 0.350000 | $2,208.84 | $773.09 |
| Suma de Mano de Obra | $904.57 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.015000 | $0.59 | $0.01 |
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOT. KHOLER 4 H. C/ OPERADOR . | HR | 0.166700 | $56.23 | $9.37 |
| Suma de Equipo | $9.38 | ||||
| Costo Directo | $1,217.77 |