| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONT17 | SOBRETAPA GALVANIZADA DE 19 MM MCA. CATUSA O SIMILAR, INCLUYE: SUMINISTRO E INSTALACION, ACARREO, TRAZO, FLETE, HERRAMIENTA, MANO DE OBRA Y LIMPIEZA EN CUALQUIER NIVEL. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOBRE TAPA 19MM | GALVANIZADA | PZA | 1.000000 | $5.89 | $5.89 |
| SOBRE TAPA 19MM | GALVANIZADA | PZA | 1.000000 | $5.89 | $5.89 |
| PIJA NO.8X1 1/4 X 1 | PIJA NO.8X1 1/4 X 1 | PZA | 2.000000 | $0.30 | $0.60 |
| PIJA NO.8X1 1/4 X 1 | PIJA NO.8X1 1/4 X 1 | PZA | 2.000000 | $0.30 | $0.60 |
| Suma de Material | $12.98 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 22 | (1Of. Electricista,1 Ayudantes) | JOR | 0.014710 | $1,057.46 | $15.56 |
| CUADRILLA NO. 22 | (1Of. Electricista,1 Ayudantes) | JOR | 0.014710 | $1,057.46 | $15.56 |
| Suma de Mano de Obra | $31.11 | ||||
| Costo Directo | $44.09 |