| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE27 | SOPORTE PARA TUBERIA A BASE DE ANGULO PINTADO CON PINTURA PRIMARIO Y NEGRO ESMALTE. INCLUYE. SUMINISTRO E INSTALACION, SOLDADURA, TAQUETE, TORNILLO, ACARREO Y LIMPIEZA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAQUETE SCI 3/8" | TAQUETE SCI 3/8" | PZA | 2.000000 | $7.50 | $15.00 |
| VARILLA ROSCADA 3/8" | VARILLA ROSC. 3/8 | ML | 0.800000 | $9.80 | $7.84 |
| TUERCA GALV. 3/8" | 0 | PZA | 2.000000 | $0.50 | $1.00 |
| ANGULO 3/16X1 1/2 | ANGULO DE 3/16 X 11/2" | ML | 0.500000 | $13.00 | $6.50 |
| PINTURA PRIMARIO | PINTURA PRIMARIO | LT | 0.025000 | $45.00 | $1.13 |
| BROCHA 2" | BROCHA DE 2" | PZA | 0.025000 | $9.50 | $0.24 |
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.025000 | $51.40 | $1.29 |
| SOLDADURA E7018 | SOLDADURA E7018 | KG | 0.050000 | $25.00 | $1.25 |
| Suma de Material | $34.24 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 22 | (1Of. Electricista,1 Ayudantes) | JOR | 0.055560 | $1,057.46 | $58.75 |
| Suma de Mano de Obra | $58.75 | ||||
| Costo Directo | $92.99 |