| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U-89-6 | DEMOLICION DE MURO DE LA COCINA PARA MODIFICAR LA INSTALACION OCULTA PARA LAS TARJAS DE LA COCINA QUE LLEGARON A LA OBRA CON DIMENSIONES DIFERENTES AL PROYECTO.INCLUYE DEMOLICIONY REPOSICION DE MURO Y AZULEJO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-02 | ACERO REF.VAR.DIAM. | KG | 3.000000 | $8.00 | $24.00 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 3.280000 | $6.00 | $19.68 |
| DIESEL | DIESEL | LT | 0.258500 | $6.00 | $1.55 |
| ACERO-01 | ALAMBRE RECOCIDO | KG | 0.200000 | $11.14 | $2.23 |
| INTERCERAMIC-01 | ADHESIVO INTERCERAMIC | KG | 4.000000 | $4.80 | $19.20 |
| BOQUILLA INTERCERAM. | BOQUILLA INTERCERAM. | KG | 1.000000 | $5.50 | $5.50 |
| DISCO ABRASIVO | Disco abrasivo para ranurar | PZA | 0.024000 | $45.00 | $1.08 |
| AZULEJO | PISO INTERCERAMIC, CLASS AZUL DE 20 X 20 MODELO PREMIER | M2 | 0.660000 | $139.00 | $91.74 |
| Suma de Material | $164.98 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.250000 | $876.53 | $219.13 |
| CUADRILLA NO. 08 | (1 Of. Azulejero + 1Ayudante). | JOR | 0.375000 | $841.63 | $315.61 |
| Suma de Mano de Obra | $534.74 | ||||
| Equipo | |||||
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOT. KHOLER 4 H. C/ OPERADOR . | HR | 0.068000 | $56.23 | $3.82 |
| ESMERILADORA | Esmeriladora | HR | 0.200000 | $10.02 | $2.00 |
| Suma de Equipo | $5.83 | ||||
| Auxiliar | |||||
| CONCRETO H/O 150 | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3 | 0.051500 | $864.00 | $44.50 |
| CONCRETO H/O 150 | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3 | 0.051500 | $864.00 | $44.50 |
| Suma de Auxiliar | $88.99 | ||||
| Costo Directo | $794.54 |