| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U-Y-3 | COLUMNA FALSA DE 0.60X1.00X2.80 M.FABRICADA CON TABLA CEMENTO Y METAL DE YESO PANAMERICANO.INCLUYE MATERIALES,HERRAJES,CINTAS ACRILICAS,BASECOAT,ANDAMIO,MANO DE OBRA ,EQUIPO Y HERRAMIENTA.(SANITARIO HOMBRES PLANTA ALTA). | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PLAFO-12 | CANALETA DE CARGA CALIBRE 22 DE 3.05 DE LARGO | PZA | 0.500000 | $17.13 | $8.57 |
| PLAFO-21 | POSTE METALICO 4.10X3.05M | PZA | 5.000000 | $27.83 | $139.15 |
| PLAFO-22 | PIJA AUTOROSCABLE PARA METAL DE 1/2" | PZA | 120.000000 | $0.30 | $36.00 |
| PLAFO-23 | PANEL DE 1.22X2.44M DE DUROCK(TABLA CEMENTO) | HOJA | 0.750000 | $324.00 | $243.00 |
| PLAFO-16 | JUNTA DE CONTROL FIRST COAT | PZA | 2.500000 | $25.00 | $62.50 |
| PLAFO-20 | TORNILLO TIPO S DE "1" | PZA | 12.330000 | $0.26 | $3.21 |
| PLAFO--25 | BASECOAT PARA JUNTEO | KG | 10.000000 | $0.00 | $0.00 |
| PLAFO-26 | CINTA PARA JUNTEO ACRILICA | ROLLO | 0.150000 | $60.87 | $9.13 |
| Suma de Material | $501.55 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 97 | (1 Of.Tablaroquero + 1 Ayud.) | Jor | 1.000000 | $867.81 | $867.81 |
| Suma de Mano de Obra | $867.81 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO metalicos | DIA | 1.000000 | $26.05 | $26.05 |
| Suma de Auxiliar | $26.05 | ||||
| Costo Directo | $1,395.41 |