| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALI-91 | TUBO CONDUIT P.V.C. TIPO R-1 (PESADO) TRAMO 3 M 51 MM | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.PVC.T.P.50MM | TUBOC PVC.T.P.50MM | ML | 1.050000 | $16.93 | $17.78 |
| GUIA ALAMBRE 14. | ALAMBRE PARA GUIA # 14 GALVANIZADO | ML | 1.030000 | $0.15 | $0.15 |
| PEGAMENTO PVC | PEGAMENTO PARA PVC. BOTE DE 500G | KG | 0.066670 | $78.50 | $5.23 |
| LIMPIADOR P/PVC | LIMPIADOR PVC 250ML | BOTE | 0.050000 | $27.00 | $1.35 |
| SEGUETA DE ACERO | SEGUETA ESTANDAR DE ACERO TRUPER | PZA | 0.018180 | $6.50 | $0.12 |
| ESTOPA | ESTOPA | Kg. | 0.002300 | $16.00 | $0.04 |
| LIJA FINA ESMERIL | LIJA FINA ESMERIL | PZA | 0.020410 | $5.80 | $0.12 |
| Suma de Material | $24.79 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 22 | (1Of. Electricista,1 Ayudantes) | JOR | 0.028570 | $1,057.46 | $30.21 |
| Suma de Mano de Obra | $30.21 | ||||
| Costo Directo | $55.00 |