| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP6 | SUMINISTRO Y COLOCACION DE TUBERIA DE PVC HIDRAULICO CEMENTAR RD/26 DE 25 MM | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBPVC-RD26-25 | TUBO DE PVC HIDRAULICO CEMENTAR , RD-26 DE 1" | ML | 1.050000 | $8.60 | $9.03 |
| PEGTANGITROS500 | PEGAMENTO TANGIT ROSADO , BOTE DE 500 ML | PZA | 0.010000 | $53.50 | $0.54 |
| LIMPIADOR-PVC-2 | LIMPIADOR PARA PVC , BOTE DE 250 ML | PZA | 0.025000 | $37.80 | $0.95 |
| LIJAESMERILFINA | LIJA DE ESMERIL FINA | PZA | 0.035000 | $15.30 | $0.54 |
| ESTOPA | ESTOPA BLANCA | KG | 0.015000 | $16.30 | $0.24 |
| SEGUETAD/STAN | SEGUETA DIENTE STANDARD | PZA | 0.015000 | $8.50 | $0.13 |
| Suma de Material | $11.42 | ||||
| Mano de Obra | |||||
| I CUAD PLOMEROS | CUADRILLA DE PLOMEROS | jor | 0.054305 | $796.13 | $43.23 |
| Suma de Mano de Obra | $43.23 | ||||
| Costo Directo | $54.65 |