| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U-65-A | RELLENO EN AZOTEAS A BASE DE CAL,CEMENTO GRIS,ARENA,TEPETZIL (MATERIAL LIGERO)EN PROPORCION DE 0.50:1:4:16 Y AGUA MEZCLANDO LOS INGREDIENTES PARA CONSEGUIR UN CONCRETO LIGERO.INCLUYE MEZCLADO,ELEVACION DE LA MEZCLA ,TENDIDO Y COMPACTADO CON PIZON DE MANO Y SELLADO CON PLANA DE MADERA,ANDAMIAJE,EQUIPO Y MANO DE OBRA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO GRIS PARA APARENTAR | TON | 0.050000 | $1,515.80 | $75.79 |
| AGREGADO-004 | ARENA | M3 | 0.000000 | $55.00 | $0.00 |
| AGREGADO-003 | AGUA | M3 | 0.100000 | $40.00 | $4.00 |
| TEPETZIL | TEPETZIL MATERIAL LIGERO | M3 | 0.250000 | $160.00 | $40.00 |
| CAL | CAL HIDRATADA | TON | 0.020000 | $1,080.00 | $21.60 |
| Suma de Material | $141.39 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones). | JOR | 0.050000 | $2,208.84 | $110.44 |
| Suma de Mano de Obra | $110.44 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.100000 | $45.00 | $4.50 |
| Suma de Herramienta | $4.50 | ||||
| Costo Directo | $256.33 |