| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PR-05 | Suministro y colocacion de estructura metalica provisional para losa actual de marcos de OR 4"x0.500 Y Placas de 1/2". De perfiles OR y placas de 1/2". | kg |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-ACERO-ESTR-02 | ANGULO . 2"X1/4" | KG | 1.050000 | $9.47 | $9.94 |
| OC-COMB-005 | GAS | KG | 0.009000 | $12.00 | $0.11 |
| OC-COMB-006 | OXIGENO | M3 | 0.010560 | $40.00 | $0.42 |
| OC-SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.015000 | $27.80 | $0.42 |
| OC-DISCO ABRASIVO | Disco abrasivo para ranurar | PZA | 0.002000 | $45.00 | $0.09 |
| OC-TUERCA 3/8" | TUERCA 3/8" | PZA | 0.509200 | $6.00 | $3.06 |
| OC-ARANDELA 3/8" | ARANDELA 3/8" | PZA | 0.509200 | $4.00 | $2.04 |
| OC-TUERCA 2H 5/8" | TUERCA 2H 5/8" | PZA | 0.109100 | $14.00 | $1.53 |
| OC-ARANDELA 5/8" | ARANDELA 5/8" | PZA | 0.109100 | $5.00 | $0.55 |
| OC-CUERDA | CUERDA | PZA | 0.473000 | $20.00 | $9.46 |
| Suma de Material | $27.61 | ||||
| Mano de Obra | |||||
| OC-CUA19 | CUADRILLA (1 PAILERO + 1 AYUD.) | JOR | 0.002500 | $930.12 | $2.33 |
| OC-CUA20 | CUADRILLA (1 SOLDADOR + 1 AYUD.) | JOR | 0.003070 | $1,046.32 | $3.21 |
| OC-CUA21 | CUADRILLA (1 MONTADOR + 4 AYUD.) | JOR | 0.001381 | $1,973.38 | $2.73 |
| Suma de Mano de Obra | $8.26 | ||||
| Herramienta | |||||
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.043821 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | hora | 0.013880 | $0.99 | $0.01 |
| ESMERILADORA | Esmeriladora | hora | 0.028440 | $9.95 | $0.28 |
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | hora | 0.011440 | $28.88 | $0.33 |
| Suma de Equipo | $0.63 | ||||
| Costo Directo | $36.50 |