| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U--30RR | DADO DE CONCRETO DE 0.43X0.43X0.25 M PARA OCULTAR BASE DE COLUMNAS METALICAS.INCLUYE CIMBRA ,CONCRETO,DESCIMBRAY APARENTADO DEL DADO VISIBLE,MATERIALES Y MANO DE OBRA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16 MM | M2 | 0.200000 | $103.00 | $20.60 |
| CLAVO | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.080000 | $16.60 | $1.33 |
| ACERO-01 | ALAMBRE RECOCIDO | KG | 0.250000 | $11.14 | $2.79 |
| SEPARADORES | Separadores | PZA | 0.075000 | $2.50 | $0.19 |
| DIESEL | DIESEL | LT | 0.300000 | $6.00 | $1.80 |
| MADERA D/PINO 3A | MADERA DE PINO DE 1A. | PT | 1.450000 | $7.12 | $10.32 |
| AGREGADO-003 | AGUA | M3 | 0.030000 | $40.00 | $1.20 |
| CONCRETO-03 | Concreto Premezclado resistencia normalF'c=250 Kg/Cm2 A.M. 3/4" SE INCLUYE revenimiento | m3 | 0.055000 | $896.80 | $49.32 |
| Suma de Material | $87.55 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Carpintero + 1Ayudante) | JOR | 0.050000 | $876.53 | $43.83 |
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones). | JOR | 0.100000 | $2,208.84 | $220.88 |
| Suma de Mano de Obra | $264.71 | ||||
| Equipo | |||||
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOT. KHOLER 4 H. C/ OPERADOR . | HR | 0.166700 | $56.23 | $9.37 |
| Suma de Equipo | $9.37 | ||||
| Costo Directo | $361.63 |