| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| GUAR0215 | CONSTRUCCION DE GUARNICION PECHO PALOMA (SECC = 0.10625 M3/ML), CONCRETO PREMEZCLADO f'c = 150 Kg/Cm2, TMA 19 MM, R.N. (10-8 CM), JUNTAS FRIAS @ 3.00 MTS, DETALLADO DEL DECLIVE EN ACCESOS A COCHERA, ACABADO ESCOBILLADO FINO, VOLTEADOR EN JUNTAS Y ARISTAS, INCLUYE: CIMBRA, DESCIMBRA, MATERIALES, HERRAMIENTA Y MANO DE OBRA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT0500 | CONCRETO PREMEZCLADO F'C= 150 Kg/cm2. | m3 | 0.109500 | $906.75 | $99.29 |
| MAT0500 | CONCRETO PREMEZCLADO F'C= 150 Kg/cm2. | m3 | 0.109500 | $906.75 | $99.29 |
| MAT0603 | CELOTEX JUNTA 1/8" | m2 | 0.160000 | $105.00 | $16.80 |
| MAT0603 | CELOTEX JUNTA 1/8" | m2 | 0.160000 | $105.00 | $16.80 |
| MAT0611 | CIMBRA METALICA PARA GUARNICION | ml | 1.000000 | $22.00 | $22.00 |
| MAT0611 | CIMBRA METALICA PARA GUARNICION | ml | 1.000000 | $22.00 | $22.00 |
| MAT0502 | CURACRETO | litro | 0.100000 | $30.50 | $3.05 |
| MAT0502 | CURACRETO | litro | 0.100000 | $30.50 | $3.05 |
| Suma de Material | $282.28 | ||||
| Mano de Obra | |||||
| MO-1003 | MAESTRO DE OBRA | jor | 0.004000 | $431.62 | $1.73 |
| MO-1003 | MAESTRO DE OBRA | jor | 0.004000 | $431.62 | $1.73 |
| MO-0103 | CUADRILLA DE COLADOS (1 OF. ALBANIL + 3 AYUDANTES) | jor | 0.040000 | $1,174.56 | $46.98 |
| MO-0103 | CUADRILLA DE COLADOS (1 OF. ALBANIL + 3 AYUDANTES) | jor | 0.040000 | $1,174.56 | $46.98 |
| Suma de Mano de Obra | $97.42 | ||||
| Herramienta | |||||
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQ111 | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONG 14 FT. | hora | 0.200000 | $28.75 | $5.75 |
| EQ111 | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONG 14 FT. | hora | 0.200000 | $28.75 | $5.75 |
| Suma de Equipo | $11.50 | ||||
| Costo Directo | $391.20 |