| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AP230200 | SONDEO Y LOCALIZACION DE TUBO DE ALIMENTACION PARA TOMA DE AGUA Y DESCARGA SANITARIA EXISTENTE, INCLUYE: EXCAVACION, RELLENO, HERRAMIENTA Y MANO DE OBRA. | TOMA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| MO-1000 | AYUDANTE GENERAL | jor | 0.500000 | $219.16 | $109.58 |
| MO-1000 | AYUDANTE GENERAL | jor | 0.500000 | $219.16 | $109.58 |
| MO-1000 | AYUDANTE GENERAL | jor | 0.500000 | $219.16 | $109.58 |
| MO-1003 | MAESTRO DE OBRA | jor | 0.050000 | $431.62 | $21.58 |
| MO-1003 | MAESTRO DE OBRA | jor | 0.050000 | $431.62 | $21.58 |
| MO-1003 | MAESTRO DE OBRA | jor | 0.050000 | $431.62 | $21.58 |
| Suma de Mano de Obra | $393.48 | ||||
| Herramienta | |||||
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $393.48 |