| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| GUAR0300 | CONSTRUCCION DE GUARNICION TRAPEZOIDAL (SECCION 0.035 M2) A BASE DE CONC. PREM. f'c=150 Kg/Cm2, TMA 19 MM, REV. NOR. (8-12 CM), VRS 3/8" Ø @ 1,0 MTS, EN ESCUADRA DE 15x25 CM DE LARGO, CON 2 VS 3/8"Ø LONGITUDINALES ,PASAJUNTAS @ 3.00 M, INCLUYE: CIMBRA, DESCIMBRA, HERRAMIENTA Y MANO DE OBRA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT0500 | CONCRETO PREMEZCLADO F'C= 150 Kg/cm2. | m3 | 0.036050 | $906.75 | $32.69 |
| MAT0500 | CONCRETO PREMEZCLADO F'C= 150 Kg/cm2. | m3 | 0.036050 | $906.75 | $32.69 |
| MAT0603 | CELOTEX JUNTA 1/8" | m2 | 0.160000 | $105.00 | $16.80 |
| MAT0603 | CELOTEX JUNTA 1/8" | m2 | 0.160000 | $105.00 | $16.80 |
| MAT0502 | CURACRETO | litro | 0.100000 | $30.50 | $3.05 |
| MAT0502 | CURACRETO | litro | 0.100000 | $30.50 | $3.05 |
| Suma de Material | $105.08 | ||||
| Mano de Obra | |||||
| MO-1003 | MAESTRO DE OBRA | jor | 0.004000 | $431.62 | $1.73 |
| MO-1003 | MAESTRO DE OBRA | jor | 0.004000 | $431.62 | $1.73 |
| MO-0103 | CUADRILLA DE COLADOS (1 OF. ALBANIL + 3 AYUDANTES) | jor | 0.040000 | $1,174.56 | $46.98 |
| MO-0103 | CUADRILLA DE COLADOS (1 OF. ALBANIL + 3 AYUDANTES) | jor | 0.040000 | $1,174.56 | $46.98 |
| Suma de Mano de Obra | $97.42 | ||||
| Herramienta | |||||
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQ111 | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONG 14 FT. | hora | 0.200000 | $28.75 | $5.75 |
| EQ111 | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONG 14 FT. | hora | 0.200000 | $28.75 | $5.75 |
| Suma de Equipo | $11.50 | ||||
| Auxiliar | |||||
| FRONT-02 | CIMBRA PARA GUARNICIONES | ml | 0.200000 | $103.73 | $20.75 |
| FRONT-02 | CIMBRA PARA GUARNICIONES | ml | 0.200000 | $103.73 | $20.75 |
| Suma de Auxiliar | $41.49 | ||||
| Costo Directo | $255.49 |