| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| DS000405 | RENIVELACION DE POZO DE VISITA CON BROCAL Y TAPA DE CONCRETO, ARMADA CON VARILLA No. 4 Y EST. No. 2 @ 15 CM, (Y/O BROCAL Y TAPA DE POLYCRETO O SIMILAR), INCLUYE: EXCAVACION, DEMOLICION, RELLENO, APLANADO INTERIOR, MATERIALES, HERRAMIENTA Y MANO DE OBRA. | POZO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT0403 | ADOBON 7 x 14 x 28 CM. | pieza | 120.000000 | $3.00 | $360.00 |
| MAT0403 | ADOBON 7 x 14 x 28 CM. | pieza | 120.000000 | $3.00 | $360.00 |
| MAT0403 | ADOBON 7 x 14 x 28 CM. | pieza | 120.000000 | $3.00 | $360.00 |
| MAT0501 | CONCRETO PREMEZCLADO f'c=300 Kg/Cm2. | m3 | 0.050000 | $1,112.00 | $55.60 |
| MAT0501 | CONCRETO PREMEZCLADO f'c=300 Kg/Cm2. | m3 | 0.050000 | $1,112.00 | $55.60 |
| MAT0501 | CONCRETO PREMEZCLADO f'c=300 Kg/Cm2. | m3 | 0.050000 | $1,112.00 | $55.60 |
| MAT0400 | BROCAL CON TAPA DE CONCRETO ARMADO | pieza | 1.000000 | $1,400.00 | $1,400.00 |
| MAT0400 | BROCAL CON TAPA DE CONCRETO ARMADO | pieza | 1.000000 | $1,400.00 | $1,400.00 |
| MAT0400 | BROCAL CON TAPA DE CONCRETO ARMADO | pieza | 1.000000 | $1,400.00 | $1,400.00 |
| Suma de Material | $5,446.80 | ||||
| Mano de Obra | |||||
| MO-0105 | CUADRILLA DE ALBANILERIA (1 OF. ALBANIL + 2 AYUDANTES) | jor | 1.000000 | $903.41 | $903.41 |
| MO-0105 | CUADRILLA DE ALBANILERIA (1 OF. ALBANIL + 2 AYUDANTES) | jor | 1.000000 | $903.41 | $903.41 |
| MO-0105 | CUADRILLA DE ALBANILERIA (1 OF. ALBANIL + 2 AYUDANTES) | jor | 1.000000 | $903.41 | $903.41 |
| MO-0106 | CUADRILLA DE EXCAVACION (2 OBREROS) | jor | 0.125000 | $438.32 | $54.79 |
| MO-0106 | CUADRILLA DE EXCAVACION (2 OBREROS) | jor | 0.125000 | $438.32 | $54.79 |
| MO-0106 | CUADRILLA DE EXCAVACION (2 OBREROS) | jor | 0.125000 | $438.32 | $54.79 |
| MO-0107 | CUADRILLA DE DEMOLICION (2 OBREROS) | jor | 0.125000 | $903.41 | $112.93 |
| MO-0107 | CUADRILLA DE DEMOLICION (2 OBREROS) | jor | 0.125000 | $903.41 | $112.93 |
| MO-0107 | CUADRILLA DE DEMOLICION (2 OBREROS) | jor | 0.125000 | $903.41 | $112.93 |
| MO-1003 | MAESTRO DE OBRA | jor | 0.150000 | $431.62 | $64.74 |
| MO-1003 | MAESTRO DE OBRA | jor | 0.150000 | $431.62 | $64.74 |
| MO-1003 | MAESTRO DE OBRA | jor | 0.150000 | $431.62 | $64.74 |
| Suma de Mano de Obra | $3,407.61 | ||||
| Herramienta | |||||
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORT P1:4 | MORTERO CEMENTO-ARENA PROP. 1:4 | M3 | 0.125000 | $1,555.89 | $194.49 |
| MORT P1:4 | MORTERO CEMENTO-ARENA PROP. 1:4 | M3 | 0.125000 | $1,555.89 | $194.49 |
| MORT P1:4 | MORTERO CEMENTO-ARENA PROP. 1:4 | M3 | 0.125000 | $1,555.89 | $194.49 |
| FRONT-01 | CIMBRA PARA BANQUETAS HASTA 10 CM. DE ESPESOR. | ml | 0.125000 | $24.31 | $3.04 |
| FRONT-01 | CIMBRA PARA BANQUETAS HASTA 10 CM. DE ESPESOR. | ml | 0.125000 | $24.31 | $3.04 |
| FRONT-01 | CIMBRA PARA BANQUETAS HASTA 10 CM. DE ESPESOR. | ml | 0.125000 | $24.31 | $3.04 |
| Suma de Auxiliar | $592.58 | ||||
| Costo Directo | $9,446.98 |