| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| MM56 | Reposici贸n parcial de defensas | M |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| DEF MET TRES CRESTAS | DEFENSA MET脕LICA DE TRES CRESTAS | ml | 0.070000 | $1,690.00 | $118.30 |
| Suma de Material | $118.30 | ||||
| Mano de Obra | |||||
| CUAD 005S | CUADRILLA 005S ARMADORES ( OFICIAL HERRERO + 2 AYUDANTES ) | jor | 0.020000 | $1,307.16 | $26.14 |
| CUAD 002-OC | CUAD 002-OC ( OFICIAL ALBANIL+PEON ) | jor | 0.020000 | $805.34 | $16.11 |
| Suma de Mano de Obra | $42.25 | ||||
| Equipo | |||||
| 03-4412 | CAMION PLATAFORMA FAMSA C/GRUA HIAB 071/A 7.5 TON.CON ALTRURA MAX.DE 12.MT.MOTOR DIESEL 140 HP | Hora | 0.050000 | $318.98 | $15.95 |
| COMP T250 | COMPRESOR INGRESOLL-RAND T250 250 CPM 105 HP | hora | 0.025000 | $250.14 | $6.25 |
| HIDRO KAR G2600VH | HIDROLAVADORA KARCHER G200VH MOTOR HONDA 5.5 HP | hora | 0.025000 | $116.98 | $2.92 |
| Suma de Equipo | $25.13 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.060000 | $918.65 | $55.12 |
| ELAB CONC OBRA | ELABORACION DE CONCRETO EN OBRA | m3 | 0.060000 | $247.99 | $14.88 |
| Suma de Auxiliar | $70.00 | ||||
| Costo Directo | $255.68 |