| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| CIMENTE-03 | Plantilla de concreto f'c = 100 Kg/cm虏 de 5 cm de espesor, para el desplante de la cimentaci贸n. El precio incluye: Suministro, colocaci贸n, materiales diversos, equipo, herramienta, mano de obra y todo lo necesario para su correcta ejecuci贸n. | m虏 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA-01 | MADERA DE PINO DE 2A. | PT | 0.450000 | $9.00 | $4.05 |
| CIMBRA-01 | MADERA DE PINO DE 2A. | PT | 0.450000 | $9.00 | $4.05 |
| CIMBRA-01 | MADERA DE PINO DE 2A. | PT | 0.450000 | $9.00 | $4.05 |
| CIMBRA-01 | MADERA DE PINO DE 2A. | PT | 0.450000 | $9.00 | $4.05 |
| CIMBRA-01 | MADERA DE PINO DE 2A. | PT | 0.450000 | $9.00 | $4.05 |
| CIMBRA-01 | MADERA DE PINO DE 2A. | PT | 0.450000 | $9.00 | $4.05 |
| CIMBRA-01 | MADERA DE PINO DE 2A. | PT | 0.450000 | $9.00 | $4.05 |
| Suma de Material | $28.35 | ||||
| Mano de Obra | |||||
| CUADRILLA 01 | CUADRILLA ( 1 ALBA脩IL + 1 PEON ) | JOR | 0.026000 | $945.49 | $24.58 |
| CUADRILLA 01 | CUADRILLA ( 1 ALBA脩IL + 1 PEON ) | JOR | 0.026000 | $945.49 | $24.58 |
| CUADRILLA 01 | CUADRILLA ( 1 ALBA脩IL + 1 PEON ) | JOR | 0.026000 | $945.49 | $24.58 |
| CUADRILLA 01 | CUADRILLA ( 1 ALBA脩IL + 1 PEON ) | JOR | 0.026000 | $945.49 | $24.58 |
| CUADRILLA 01 | CUADRILLA ( 1 ALBA脩IL + 1 PEON ) | JOR | 0.026000 | $945.49 | $24.58 |
| CUADRILLA 01 | CUADRILLA ( 1 ALBA脩IL + 1 PEON ) | JOR | 0.026000 | $945.49 | $24.58 |
| CUADRILLA 01 | CUADRILLA ( 1 ALBA脩IL + 1 PEON ) | JOR | 0.026000 | $945.49 | $24.58 |
| Suma de Mano de Obra | $172.08 | ||||
| Auxiliar | |||||
| CONCRETO100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.060000 | $1,043.74 | $62.62 |
| CONCRETO100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.060000 | $1,043.74 | $62.62 |
| CONCRETO100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.060000 | $1,043.74 | $62.62 |
| CONCRETO100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.060000 | $1,043.74 | $62.62 |
| CONCRETO100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.060000 | $1,043.74 | $62.62 |
| CONCRETO100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.060000 | $1,043.74 | $62.62 |
| CONCRETO100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.060000 | $1,043.74 | $62.62 |
| Suma de Auxiliar | $438.37 | ||||
| Costo Directo | $638.80 |