| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 090105 | Fajas en arenon | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARENON | Arenon chino N° 1 25 kg | un | 4.210000 | $11,500.00 | $48,415.00 |
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 0.125000 | $21,704.00 | $2,713.00 |
| VARD3 | Varilla dilatacion 3mm cobre | ml | 0.100000 | $8,173.00 | $817.30 |
| Suma de Material | $51,945.30 | ||||
| Mano de Obra | |||||
| ZCUADPIS | Cuadrilla Pisos | jor | 0.082500 | $121,896.00 | $10,056.42 |
| Suma de Mano de Obra | $10,056.42 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $62,001.72 |