| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050604 | Dinteles concreto 15x20 | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.060137 | $115,595.00 | $6,951.54 |
| Suma de Mano de Obra | $6,951.54 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 0.032000 | $5,000.00 | $160.00 |
| Suma de Auxiliar | $160.00 | ||||
| Concepto | |||||
| 050113 | Formaleta dintel concreto visto | ml | 0.200000 | $14,665.00 | $2,933.00 |
| 050203 | Concreto 3000 psi en obra | m3 | 0.032000 | $294,870.00 | $9,435.84 |
| 040206 | Refuerzo de 60.000 psi | kg | 4.300000 | $2,910.00 | $12,513.00 |
| Suma de Concepto | $24,881.84 | ||||
| Costo Directo | $31,993.38 |