| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 080213 | Imperm s/cimiento M15-3 caras con mortero | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SIKA1 | Sika 1 impermeabilizante integral (20 kg) | kg | 0.880000 | $5,429.00 | $4,777.52 |
| Suma de Material | $4,777.52 | ||||
| Mano de Obra | |||||
| ZCUADIMP | Cuadrilla Impermeabilizaciones | jor | 0.049359 | $124,054.00 | $6,123.18 |
| Suma de Mano de Obra | $6,123.18 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.230000 | $1,000.00 | $230.00 |
| Suma de Auxiliar | $230.00 | ||||
| Concepto | |||||
| 050215 | Mortero 1:3 de revoque | m3 | 0.025000 | $325,061.00 | $8,126.53 |
| Suma de Concepto | $8,126.53 | ||||
| Costo Directo | $19,257.23 |