| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110211 | Tubo concreto 24 uec. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOCONCRE20 | Tubo concreto sin refuerzo D=24" L=1.2m cl2 | ml | 1.030000 | $144,492.00 | $148,826.76 |
| ENSAYOT18 | Ensayo de tuberia | gl | 1.000000 | $1,259.00 | $1,259.00 |
| Suma de Material | $150,085.76 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.172000 | $118,357.00 | $20,357.40 |
| Suma de Mano de Obra | $20,357.40 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETR1 | Retroexcavadora | hr | 0.100000 | $70,000.00 | $7,000.00 |
| Suma de Equipo | $7,000.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 2.900000 | $1,000.00 | $2,900.00 |
| Suma de Auxiliar | $2,900.00 | ||||
| Costo Directo | $180,343.16 |