| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 060201 | Cubierta teja de barro | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TEJABAR | Teja barro comun | un | 19.000000 | $700.00 | $13,300.00 |
| ABARCO255 | Abarco 2"x5"x5 varas | un | 0.500000 | $17,067.00 | $8,533.50 |
| ABARCO256 | Abarco 2"x5"x6 varas | un | 0.500000 | $24,833.00 | $12,416.50 |
| CARGABARCO | Carguera abarco prensada 4x10"x8 varas | un | 0.066670 | $190,690.00 | $12,713.30 |
| BARNIZ | Barniz brillante exterior | gal | 0.025000 | $27,756.00 | $693.90 |
| BASETP | Base tapa poros incoloro ref 7203 | gal | 0.025000 | $35,708.00 | $892.70 |
| INMUN | Inmunizante madera incoloro (1 gal) | gal | 0.025000 | $27,900.00 | $697.50 |
| PERMO | Permofit (Rollo 24 x 1m de 1.2 mm) | un | 0.117650 | $136,862.00 | $16,101.81 |
| TABLILLAP | Tablilla pino patula | m2 | 1.100000 | $12,693.00 | $13,962.30 |
| CERCHAM | Cercha en abarco tipo w | un | 0.011110 | $2,456,041.00 | $27,286.62 |
| TORNIG09 | Tornillos galvanizados (Juego) | un | 0.050000 | $13,045.00 | $652.25 |
| DISESTR | Diseño estructural | un | 0.005560 | $588,500.00 | $3,272.06 |
| Suma de Material | $110,522.44 | ||||
| Mano de Obra | |||||
| ZCUADCUB | Cuadrilla Cubierta | jor | 0.125000 | $121,896.00 | $15,237.00 |
| Suma de Mano de Obra | $15,237.00 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OBRAFALSA | Obra falsa (alquiler) | dÃa | 0.012150 | $4,365.00 | $53.03 |
| PULIDOMA | Pulidora manual (sin disco) | dÃa | 0.166670 | $17,168.00 | $2,861.39 |
| CIRCULAR | Circular para madera (alquiler) | dÃa | 0.166670 | $20,000.00 | $3,333.40 |
| Suma de Equipo | $6,247.83 | ||||
| Auxiliar | |||||
| TRVER | Transporte vertical | dia | 0.020000 | $192,509.00 | $3,850.18 |
| Suma de Auxiliar | $3,850.18 | ||||
| Costo Directo | $135,857.45 |