| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 220108 | Cañuela en tejon de concreto | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TEJON8 | Tejon concreto 8 | ml | 1.050000 | $5,578.00 | $5,856.90 |
| Suma de Material | $5,856.90 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.019118 | $115,595.00 | $2,209.95 |
| Suma de Mano de Obra | $2,209.95 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.150000 | $1,000.00 | $150.00 |
| Suma de Auxiliar | $150.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.005000 | $285,872.00 | $1,429.36 |
| Suma de Concepto | $1,429.36 | ||||
| Costo Directo | $9,646.21 |