| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070302 | Muro en gaviones triple torsion | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLAGAV01 | Malla gavion 1x1x1 | un | 0.070000 | $60,509.00 | $4,235.63 |
| MALLAGAV10 | Malla gavion 2x1x1 | un | 0.110000 | $71,050.00 | $7,815.50 |
| MALLAGAV20 | Malla gavion 3x1x1 | un | 0.220000 | $102,950.00 | $22,649.00 |
| ALAMBRGC16 | Alambre galvanizado C16 | kg | 2.000000 | $4,000.00 | $8,000.00 |
| PIEDRA | Piedra (sum + transp) | m3 | 1.050000 | $40,334.00 | $42,350.70 |
| Suma de Material | $85,050.83 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.226471 | $115,595.00 | $26,178.92 |
| Suma de Mano de Obra | $26,178.92 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| FORMALETA | Formaleta | gl | 5.000000 | $1,000.00 | $5,000.00 |
| Suma de Equipo | $5,000.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 1.050000 | $5,000.00 | $5,250.00 |
| TRMAT | Transporte materiales | glo | 0.271000 | $1,000.00 | $271.00 |
| Suma de Auxiliar | $5,521.00 | ||||
| Costo Directo | $121,750.75 |