| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130803 | Tablero de energia | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABLEROTRI30 | Tablero trifasico 12 ctos | un | 1.000000 | $140,903.00 | $140,903.00 |
| INTERRUP02 | Interruptor 1x20-1x50 amp westing | un | 6.000000 | $8,568.00 | $51,408.00 |
| INTERRUP01 | Interruptor 2x20-2x50 amp westing | un | 2.000000 | $21,896.00 | $43,792.00 |
| VARIO | Varios electricos | un | 2.000000 | $1,318.00 | $2,636.00 |
| Suma de Material | $238,739.00 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 1.277000 | $116,803.00 | $149,157.43 |
| Suma de Mano de Obra | $149,157.43 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 10.000000 | $1,000.00 | $10,000.00 |
| Suma de Auxiliar | $10,000.00 | ||||
| Costo Directo | $397,896.43 |