| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040102 | Ciclopeo. | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIEDRA | Piedra (sum + transp) | m3 | 0.420000 | $40,334.00 | $16,940.28 |
| Suma de Material | $16,940.28 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.224920 | $115,595.00 | $25,999.63 |
| Suma de Mano de Obra | $25,999.63 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 1.050000 | $5,000.00 | $5,250.00 |
| Suma de Auxiliar | $5,250.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 0.630000 | $294,870.00 | $185,768.10 |
| Suma de Concepto | $185,768.10 | ||||
| Costo Directo | $233,958.01 |