| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050210 | Mortero 1:4 impermeabilizado | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SIKA1 | Sika 1 impermeabilizante integral (20 kg) | kg | 0.800000 | $5,429.00 | $4,343.20 |
| Suma de Material | $4,343.20 | ||||
| Mano de Obra | |||||
| ZCUADREV | Cuadrilla Revoques | jor | 0.062330 | $116,803.00 | $7,280.33 |
| Suma de Mano de Obra | $7,280.33 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 0.025000 | $5,000.00 | $125.00 |
| Suma de Auxiliar | $125.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.025000 | $285,872.00 | $7,146.80 |
| Suma de Concepto | $7,146.80 | ||||
| Costo Directo | $18,895.33 |