| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 100109 | Enchape en piedra royal veta 60x30x1 | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIEDROYALV2 | Piedra royal verde - dorado de 60x30 e=1 cm, natural | m2 | 1.030000 | $98,600.00 | $101,558.00 |
| OXAL | Oxalico | lb | 0.070000 | $3,484.00 | $243.88 |
| OXNIT | Oxido nitrico | gal | 0.040000 | $6,207.00 | $248.28 |
| ACIDOMUR | Acido muriatico (cuñete) | un | 0.010000 | $28,940.00 | $289.40 |
| MALLAPOLLO | Malla pollo | m2 | 1.200000 | $1,204.00 | $1,444.80 |
| SIKALAT | Sika latex aditivo adherente para morteros (20kg) - Sika | kg | 0.060000 | $21,692.00 | $1,301.52 |
| PEGACG01 | Pegacor gris exteriores (25kg) - Sumicol | kg | 3.000000 | $1,553.00 | $4,659.00 |
| Suma de Material | $109,744.88 | ||||
| Mano de Obra | |||||
| SUBCONT | Subcontratista | gl | 22.000000 | $1,000.00 | $22,000.00 |
| Suma de Mano de Obra | $22,000.00 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OBRAFALSA | Obra falsa (alquiler) | día | 0.121540 | $4,365.00 | $530.52 |
| Suma de Equipo | $530.52 | ||||
| Costo Directo | $132,275.40 |