| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110605 | Camara caida 10 | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.376471 | $115,595.00 | $43,518.17 |
| Suma de Mano de Obra | $43,518.17 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETR1 | Retroexcavadora | hr | 0.125000 | $70,000.00 | $8,750.00 |
| Suma de Equipo | $8,750.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.300000 | $1,000.00 | $300.00 |
| Suma de Auxiliar | $300.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 1.670000 | $294,870.00 | $492,432.90 |
| 110203 | Tubo concreto 10 uec. | ml | 1.030000 | $42,923.00 | $44,210.69 |
| Suma de Concepto | $536,643.59 | ||||
| Costo Directo | $589,211.76 |