| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 010543 | Reubicacion de postes energia | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BASEGR | Base granular (area metropolitana) | m3 | 0.600000 | $25,056.00 | $15,033.60 |
| Suma de Material | $15,033.60 | ||||
| Mano de Obra | |||||
| ZCUADRET | Cuadrilla Retiros | jor | 0.699301 | $107,037.00 | $74,851.08 |
| Suma de Mano de Obra | $74,851.08 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| GRUA | Grúa 300 con winche | dia | 0.233330 | $300,000.00 | $69,999.00 |
| COMPACT01 | Compactador tipo Canguro (alquiler) | día | 0.500000 | $65,000.00 | $32,500.00 |
| Suma de Equipo | $102,499.00 | ||||
| Auxiliar | |||||
| TRZAGR20 | Transporte pétreos | m3 | 1.000000 | $20,571.00 | $20,571.00 |
| Suma de Auxiliar | $20,571.00 | ||||
| Costo Directo | $212,954.68 |