| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 010414 | Demol de cordones. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADDEM | Cuadrilla Demoliciones | jor | 0.075080 | $107,037.00 | $8,036.34 |
| Suma de Mano de Obra | $8,036.34 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 0.225000 | $5,000.00 | $1,125.00 |
| Suma de Auxiliar | $1,125.00 | ||||
| Concepto | |||||
| 020402 | Cargue (Paleros)-transp-botada. | m3 | 0.225000 | $27,048.00 | $6,085.80 |
| Suma de Concepto | $6,085.80 | ||||
| Costo Directo | $15,247.14 |