| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 020509 | Llenos en triturado 1½" | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRITU03 | Triturado 1½" | m3 | 1.200000 | $38,280.00 | $45,936.00 |
| Suma de Material | $45,936.00 | ||||
| Mano de Obra | |||||
| ZCUADMT | Cuadrilla Mvto de tierra | jor | 0.056060 | $107,037.00 | $6,000.49 |
| Suma de Mano de Obra | $6,000.49 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRZAGR10 | Transporte triturado | m3 | 1.200000 | $19,800.00 | $23,760.00 |
| TRLOC | Transporte local | m3 | 1.200000 | $5,000.00 | $6,000.00 |
| Suma de Auxiliar | $29,760.00 | ||||
| Costo Directo | $81,696.49 |