| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 090120 | Piso en corcho y arenon | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABLETA08 | Tableta corcho 10*10 | m2 | 0.672000 | $13,976.00 | $9,391.87 |
| ARENON | Arenon chino N° 1 25 kg | un | 8.160000 | $11,500.00 | $93,840.00 |
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 0.495000 | $21,704.00 | $10,743.48 |
| Suma de Material | $113,975.35 | ||||
| Mano de Obra | |||||
| ZCUADPIS | Cuadrilla Pisos | jor | 0.096250 | $121,896.00 | $11,732.49 |
| Suma de Mano de Obra | $11,732.49 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 2.000000 | $1,000.00 | $2,000.00 |
| Suma de Auxiliar | $2,000.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.020000 | $285,872.00 | $5,717.44 |
| Suma de Concepto | $5,717.44 | ||||
| Costo Directo | $133,425.28 |