| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050201 | Concreto 2000 psi en obra | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 5.720000 | $21,704.00 | $124,146.88 |
| ARENAFINA | Arena fina para concretos | m3 | 0.693000 | $33,826.00 | $23,441.42 |
| TRITU02 | Triturado 3/4" | m3 | 0.882000 | $38,280.00 | $33,762.96 |
| AGUA | Agua | lt | 163.000000 | $50.00 | $8,150.00 |
| Suma de Material | $189,501.26 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.216270 | $115,595.00 | $24,999.73 |
| Suma de Mano de Obra | $24,999.73 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MEZCLADORA | Mezcladora trompo eléctrica 1.5 sacos / operador | día | 0.200000 | $72,672.00 | $14,534.40 |
| Suma de Equipo | $14,534.40 | ||||
| Auxiliar | |||||
| TRZAGR01 | Transporte arena | m3 | 0.693000 | $19,800.00 | $13,721.40 |
| TRZAGR10 | Transporte triturado | m3 | 0.882000 | $19,800.00 | $17,463.60 |
| Suma de Auxiliar | $31,185.00 | ||||
| Costo Directo | $260,220.39 |