| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110606 | Cilindro mh d=1.20m prefabricado | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIL1.2 | Cilindro pref manhole h=1m d= 1.20m | un | 1.000000 | $365,400.00 | $365,400.00 |
| GANEM | Gancho escalon manhole | un | 5.000000 | $9,699.00 | $48,495.00 |
| Suma de Material | $413,895.00 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.147000 | $115,595.00 | $16,992.47 |
| Suma de Mano de Obra | $16,992.47 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETR1 | Retroexcavadora | hr | 0.250000 | $70,000.00 | $17,500.00 |
| Suma de Equipo | $17,500.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.010000 | $285,872.00 | $2,858.72 |
| Suma de Concepto | $2,858.72 | ||||
| Costo Directo | $451,246.19 |