| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050606 | Dinteles concreto 20x20 | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.066819 | $115,595.00 | $7,723.94 |
| Suma de Mano de Obra | $7,723.94 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 0.044000 | $5,000.00 | $220.00 |
| Suma de Auxiliar | $220.00 | ||||
| Concepto | |||||
| 050113 | Formaleta dintel concreto visto | ml | 0.400000 | $14,665.00 | $5,866.00 |
| 050203 | Concreto 3000 psi en obra | m3 | 0.044000 | $294,870.00 | $12,974.28 |
| 040206 | Refuerzo de 60.000 psi | kg | 4.300000 | $2,910.00 | $12,513.00 |
| Suma de Concepto | $31,353.28 | ||||
| Costo Directo | $39,297.22 |