| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110208 | Tubo concreto 18 uec. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOCONCRE18 | Tubo concreto sin refuerzo D=18" L=1.2m cl2 | ml | 1.030000 | $82,939.00 | $85,427.17 |
| ENSAYOT18 | Ensayo de tuberia | gl | 1.000000 | $1,259.00 | $1,259.00 |
| Suma de Material | $86,686.17 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.128205 | $118,357.00 | $15,173.96 |
| Suma de Mano de Obra | $15,173.96 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETR1 | Retroexcavadora | hr | 0.045450 | $70,000.00 | $3,181.50 |
| Suma de Equipo | $3,181.50 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 2.000000 | $1,000.00 | $2,000.00 |
| Suma de Auxiliar | $2,000.00 | ||||
| Costo Directo | $107,041.63 |