| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130105 | Acometida 2#2 + 1#4 cu-thw tubo pvc 2" | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CABLECOBT02/0 | Cable cobre THHN/THWN 2/0 awg | ml | 2.000000 | $26,488.00 | $52,976.00 |
| CABLECOBT04 | Cable cobre THHN/THWN 4 awg | ml | 1.000000 | $8,358.00 | $8,358.00 |
| CINTAS23 | Cinta scotch 23 18mmx9.1 m | un | 0.010000 | $35,862.00 | $358.62 |
| CINTAS33 | Cinta sctch 33 19mmx8m | un | 0.020000 | $13,952.00 | $279.04 |
| TUBOPVCO50 | Tubo pvc-conduit 2" - Pavco | ml | 1.000000 | $26,480.00 | $26,480.00 |
| CONECTOR01 | Conector tornillo partido KS-22 2 | un | 0.300000 | $4,664.00 | $1,399.20 |
| VARIO | Varios electricos | un | 0.200000 | $1,318.00 | $263.60 |
| Suma de Material | $90,114.46 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.098340 | $116,803.00 | $11,486.41 |
| Suma de Mano de Obra | $11,486.41 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.040000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $101,600.87 |