| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110618 | Rotura y emboquillada a manhole | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.117647 | $115,595.00 | $13,599.40 |
| Suma de Mano de Obra | $13,599.40 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| COMPRES01 | Compresor un martillo (alquiler) | hr | 2.000000 | $58,000.00 | $116,000.00 |
| Suma de Equipo | $116,000.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 7.000000 | $1,000.00 | $7,000.00 |
| Suma de Auxiliar | $7,000.00 | ||||
| Concepto | |||||
| 020402 | Cargue (Paleros)-transp-botada. | m3 | 1.000000 | $27,048.00 | $27,048.00 |
| Suma de Concepto | $27,048.00 | ||||
| Costo Directo | $163,647.40 |