| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050204 | Concreto 3500 psi en obra | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 9.240000 | $21,704.00 | $200,544.96 |
| ARENAFINA | Arena fina para concretos | m3 | 0.737000 | $33,826.00 | $24,929.76 |
| TRITU02 | Triturado 3/4" | m3 | 0.703500 | $38,280.00 | $26,929.98 |
| AGUA | Agua | lt | 200.000000 | $50.00 | $10,000.00 |
| Suma de Material | $262,404.70 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.259530 | $115,595.00 | $30,000.37 |
| Suma de Mano de Obra | $30,000.37 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MEZCLADORA | Mezcladora trompo eléctrica 1.5 sacos / operador | dÃa | 0.200000 | $72,672.00 | $14,534.40 |
| Suma de Equipo | $14,534.40 | ||||
| Auxiliar | |||||
| TRZAGR01 | Transporte arena | m3 | 0.737000 | $19,800.00 | $14,592.60 |
| TRZAGR10 | Transporte triturado | m3 | 0.703500 | $19,800.00 | $13,929.30 |
| Suma de Auxiliar | $28,521.90 | ||||
| Costo Directo | $335,461.37 |