| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130624 | Salida tomacorriente pata trabada | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOPVCO20 | Tubo pvc-conduit 3/4" - Pavco | ml | 7.000000 | $6,307.00 | $44,149.00 |
| CAJAGAL05 | Caja galvanizada 4x4 cumple norma retie | un | 1.000000 | $1,835.00 | $1,835.00 |
| ALAMBRCOB06 | Alambre cobre desnudo 6 awg | ml | 21.000000 | $5,157.00 | $108,297.00 |
| CURPVC01 | Curva pvc conduit ½ | un | 2.000000 | $599.00 | $1,198.00 |
| ZUMBADOR | Zumbador 70 db 127V PRM44081 | un | 1.000000 | $16,821.00 | $16,821.00 |
| CONECTOR20 | Conector tornillo partido KS-25 1/0 | un | 3.000000 | $7,420.00 | $22,260.00 |
| VARIO | Varios electricos | un | 0.100000 | $1,318.00 | $131.80 |
| Suma de Material | $194,691.80 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.063900 | $116,803.00 | $7,463.71 |
| Suma de Mano de Obra | $7,463.71 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 1.000000 | $1,000.00 | $1,000.00 |
| Suma de Auxiliar | $1,000.00 | ||||
| Costo Directo | $203,155.51 |