| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2105 | Guayabo h=70 cm | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARBOLGUAYABO | Arbol guayabo h=70 cm | un | 1.000000 | $20,300.00 | $20,300.00 |
| Suma de Material | $20,300.00 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.010217 | $118,357.00 | $1,209.25 |
| Suma de Mano de Obra | $1,209.25 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.100000 | $1,000.00 | $100.00 |
| TRMAT | Transporte materiales | glo | 0.100000 | $1,000.00 | $100.00 |
| Suma de Auxiliar | $200.00 | ||||
| Concepto | |||||
| 2101 | Abono para huecos d=30 h=30cm | un | 1.000000 | $848.00 | $848.00 |
| Suma de Concepto | $848.00 | ||||
| Costo Directo | $22,557.25 |