| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 060309 | Tubo galvanizado 2½" | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOGA24 | Tubo galvanizado 2½" | ml | 1.030000 | $41,674.00 | $42,924.22 |
| UNIONGA2.5 | Union galv 2 1/2" | un | 0.400000 | $14,492.00 | $5,796.80 |
| CODOGA04 | Codo galv 2½" x 90 | un | 0.400000 | $22,985.00 | $9,194.00 |
| TEEGAL25 | Tee galv 2 1/2" | un | 0.400000 | $53,887.00 | $21,554.80 |
| Suma de Material | $79,469.82 | ||||
| Mano de Obra | |||||
| ZCUADLAT | Cuadrilla Latoneria | jor | 0.017188 | $121,896.00 | $2,095.15 |
| Suma de Mano de Obra | $2,095.15 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OBRAFALSA | Obra falsa (alquiler) | dÃa | 0.121540 | $4,365.00 | $530.52 |
| TARRA | Tarraja dado entero | dÃa | 0.100000 | $11,950.00 | $1,195.00 |
| Suma de Equipo | $1,725.52 | ||||
| Costo Directo | $83,290.49 |