| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 190205 | Poyo en concreto, enchapado en granito | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MESONCO | Meson cocina a=0.60m acabado granito | ml | 1.000000 | $134,255.00 | $134,255.00 |
| Suma de Material | $134,255.00 | ||||
| Mano de Obra | |||||
| ZCUADOBL | Cuadrilla Obra Blanca | jor | 0.100000 | $121,896.00 | $12,189.60 |
| Suma de Mano de Obra | $12,189.60 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.030000 | $285,872.00 | $8,576.16 |
| Suma de Concepto | $8,576.16 | ||||
| Costo Directo | $155,020.76 |