| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130116 | Vestida transformador 1 fase | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| VARCOOP1 | Varilla cooperwell 1"x=2.40m | un | 1.000000 | $36,400.00 | $36,400.00 |
| PARAR | Pararrayos OB 10KA-10KVPDV-100 | un | 1.000000 | $92,960.00 | $92,960.00 |
| CORTAC2 | Cortacircuitos 20KA 10KV | un | 1.000000 | $174,720.00 | $174,720.00 |
| ALAMBRCOB12 | Alambre cobre desnudo 12 awg | ml | 13.000000 | $1,106.00 | $14,378.00 |
| TORNIE10 | Tornillo espaciador 5/8 x 12 | un | 3.000000 | $8,000.00 | $24,000.00 |
| CONECTR01 | Conector transversal universal 1/0 | un | 2.000000 | $24,380.00 | $48,760.00 |
| ALAMBRCOB10 | Alambre cobre desnudo 10 awg | ml | 8.000000 | $1,733.00 | $13,864.00 |
| FUSIB01 | Fusible primario 5H | un | 1.000000 | $4,203.00 | $4,203.00 |
| VARIO | Varios electricos | un | 1.600000 | $1,318.00 | $2,108.80 |
| Suma de Material | $411,393.80 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 1.404853 | $116,803.00 | $164,091.04 |
| Suma de Mano de Obra | $164,091.04 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.010000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 17.000000 | $1,000.00 | $17,000.00 |
| Suma de Auxiliar | $17,000.00 | ||||
| Costo Directo | $592,484.84 |